Just had a quick squint at the plans - can't seem to identify the changing rooms for the pool. Unless it is the ones in the adjacent building; surely somebody can find them for me?
Theyre there on the right hand side of the pool. To me it looks like lots of cubicles but Im not good at plans I prefer pictures.
lets hope the design of the changing rooms in wick are better than those in portree high as it was discovered after the school opened that you could see in to the female changing area from the carpark
I kent his faither
February 2014 Stakeholders Newsletter for latest updates at http://www.highland.gov.uk/NR/rdonly...ewsletter6.pdf
Where can you see a detailed design and visualisation of the swimming pool?
The Wick Project
Newsletter 7 – April 2014
The Wick Schools Project
The Wick Schools Project includes the Wick Campus (incorporating the ‘South of the River’ Primary School, High School and East Caithness Community Facilities) on the Wick High/Pulteneytown Academy Primary School site, and the new ‘North of the River’ Primary School to be built on the current North Primary School site.
This Newsletter brings everybody up to date with progress on the whole project in Wick.
On the Web
This newsletter, together with newsletters 1 to 6, minutes of Stakeholder Meetings, together with plans of the new facilities are available at http://www.highland.gov.uk/learningh...ck+Project.htm
The Wick Campus
Newsletter 6 had dates for Stage 2 submission, and Financial Close in March 2014.
These have not yet happened, mainly due to significant work required by Hub/Miller Construction to clarify the submitted tenders.
Hub have indicated that tender costs will be shared with the Council early this month, with the Stage 2 submission following discussions between Hub and Council.
To ensure that the projected Handover Date (before Easter 2016) is maintained, the Council and Hub have already engaged in discussions regarding Early Works Contracts to allow work to start on site. (This process has already been used on the new Primary School site in the North of the River).
These contracts would include site set up, and ground works to level the site ready for building, and would last up to 8 to 10 weeks.
Project Dates
• Handover Date – before Easter 2016
• Move in period – before and during Easter 2016
• Completion of external works – August 2016
Wick North of the River Primary SchoolProgress
An Enabling Works package started in February as planned. This package consisted of site set up, a new temporary playground, hoarding and drain diversion works.
The old janitor’s house, and the wooden building adjacent is being used by Hub/Millers as site offices, and are currently being renovated.
The new temporary playground below is now complete, and pupils are now using it. (The weather looks good too!)
Photo in the Pdf version at http://www.highland.gov.uk/NR/rdonly...ewsletter7.pdf
Hoarding separating the construction site from the North Primary School is almost complete.
The drain diversion works are due to take place over the Easter holidays.
A further Enabling Works contract for groundworks is currently being discussed between Hub and the Council.
Project Dates
• School handover – 10/07/15
• Completion of all external works – 26/02/16
Safer Routes to School
ECS and TECS have met to discuss the proposals, and the outcome of these discussions will be provided at the next Stakeholder Meeting.
Stakeholder Meeting
The next Stakeholder Meeting takes place on Monday 19th May at 7pm in Wick High School.
All the drawings and plans tha tare currently available can be found at http://www.highland.gov.uk/learningh...+and+Plans.htm
I am not aware that detailed drawings of the swimming pool have been released online as yet.
Latest photos of Wick High at http://www.caithness.org/atoz/wick/p...=107&start=108
Does anyone have any advice on what we can do about the loss of the school bus Staxigoe / Papigoe pupils? It is shameful that it is deemed acceptable for the kids to have to walk over two miles in all weathers to get to school. When choosing where to live, transport to school was a considered factor in the decision making. Now there is no option for our local children
Stagecoach have agreed to reinstate the bus service for school pupils from Staxigoe.
Forthcoming Feb 2nd 2016 Stakeholder meeting. If anyone has any issues to raise with regard to Noss Primary or the Community Campus please PM me or submit to the Wick Community Council website or FACEBOOK page.
Thank you
I kent his faither
Does anyone know if the new swimming pool will have a ramp actually in the swimming pool for disabled access please?
Hi, no ramp for disabled access, however there will be steps and a hoist specifically for disabled persons in addition to a ladder at the shallow end