View Full Version : Beauly to Denny 400kV overhead Construction Works - Potential Overnight A9 Closures



NewsBot
17-May-14, 18:30
The Caithness Business Index (http://www.caithness-business.co.uk) has posted the following article:

Beauly to Denny 400kV overhead Construction Works - Potential Overnight A9 Closures




As part of the project to install a new overhead electricity transmission line between Beauly and Denny, Balfour Beatty, on behalf of Scottish Hydro Electric (SHE) Transmission, require several short night-time closures, for a maximum of three nights, to allow essential overhead cabling activities across the A9 at Dalnacardoch, 11 miles north of Blair Atholl. John Buchan, Overhead Line Project Manager for SHE Transmission said: â [Read Full Article (http://www.caithness-business.co.uk/article.php?id=4945)]